PFLNG SATU – Mooring & Hook up

PFLNG SATU – Mooring & Hook up

PFLNG SATU – Mooring & Hook up

Location : Malaysia
Project Type : Floating LNG Vessel + AHTS
Date : 2016

SCOPE OF WORK

Intervention on turret mooring chain hook-up procedure and commissioning risers:

  1. moveable sheave positioning
  2. winch rope routing and preparation
  3. winch rope recovery
  4. chain subsea recovery
  5. chain handover to PFLNG main winch
  6. final tensioning and angle measurement

Type of personnel: Mooring masters – Rigging Team

DESCRIPTION OF THE PROJECT

PFLNG SATU is the second FLNG development in the world after the Prelude FLNG, which is being developed by Shell and is expected to come on stream in 2017.

PETRONAS Floating Liquefied Natural Gas (PFLNG) is a Liquefied Natural Gas (LNG) facility custom-built as a vessel to liquefy, produce, store and offload LNG. The Petronas Floating LNG will capitalize on the availability of the gas resulting from the development of several gas fields in Malaysia. The design basis is based on new built vessel.

Construction of the facility started in June 2013 and was completed in March 2016.
Our team has been involved on the offshore installation phase: station-keeping, chain hookup, riser installation and pre-commissioning.